January Update - Elevator

January 2019

This month has been busy with rough plumbing in ground completed, the scaffolding for the elevator and stairs being completed as well as the backfilling at the retention basin. We also drilled aggregate piers at the North parcel, continued to haul rock and continued working on the sewer/water install at the North parcel.

In February look for the first-floor steel to go in and watch Edwardsville’s tallest building be erected.