November 2018

Fireside Financial celebrated the Groundbreaking Ceremony for their Whispering Heights development on November 6th, 2018.  Fireside Financial has partnered with some of the best teams in the area. Holland Construction – General Contractor, Gray Design – Architect, Hearth Construction Management – Owner Representative, Alper Audi – Engineering, Solutions AEC – MEP Engineering & Oates Associates – Structural

Read More »

October 2018

October shaped up to be an excellent month for progress on the job site. Our teams were able to complete the install for Ameren and Charter in the conduit dug from last month. Foundation crews were able to install the forced stone piers for the foundation at the South Lot. JF Electric from Edwardsville has been working

Read More »

September 2018

It’s been a busy month to start building Whispering Heights. We have excavated tons of dirt off the site in order to prep for our foundation work and boring for the underground utilities. We had to remove previous landscape items, lighting, boulders and asphalt to be able to dig enough dirt to set our base for the

Read More »

Want to see LIVE VIDEO

of what's happening now?

Close Menu